Balmoston Site Updates

May 2024

Construction is well underway for the new Balmoston homes. Here are the latest site updates, to keep the community informed of how things are progressing in relation to homes and the recreational hub:

Construction Update

  • Construction works in the public realm are complete along Portrane and The Link Rd with the Link Rd now reopened.
  • The first timber frame kits for the housing units have arrived to site in April on programme.
  • The precast frame for apartment blocks is progressing well and they are erected up to second floor.
  • The project is on programme.

Balmoston Recreation

al Hub 

 

The new Recreational Hub for the area will include a new all-weather pitch, athletics track and other sporting facilities. The facilities proposed will support and strengthen existing recreational facilities and will be accessible to existing and new communities. The hub is expected to be developed during 2024 and 2025.

Check here for regular site updates and