Glenveagh logo
Customer site
Main Menu
Home
About us

What we do

Investors

Sustainability

Corporate news

Careers

Land
Glenveagh logo
  • Customer site
  • NUA Manufacturing
  • About us
  • What we do
  • Investors
  • Sustainability
  • Corporate news
  • Careers
  • Land

Glenveagh in the Local Community

  • Community-Balgriffin

Glenveagh Supports St Brendan’s United FC with New Kit Bags

  • Community-Balgriffin

Glenveagh Sponsors St. Columban's SYC Girls Team

  • Community-Balgriffin

Talking Site Safety at Scoil Fhursa 

Balgriffin Community Hub

Find out what's new, from Glenveagh events and initiatives to site updates, to community news in Balgriffin and the surrounding areas.

Site Updates September 2026

Belcamp


Construction works in Belcamp are currently underway and are progressing on schedule. The new community, comprising a total of 78 units, will bring much needed A-rated homes to the area. The first homeowners collected their keys in December 2025, with the remaining homes expected to be completed in the coming months.

 

Resurfacing Works

As part of the Taking in Charge process, remedial works to the River Walk will recommence Wednesday 16th September and take approx. 2 days to complete.

 

Resurfacing works on College Avenue are now complete. To facilitate the opening of the playground at Washington Green, the Contractor has been asked to prioritise the footpath repair works within the playground on Friday, 4th September

 

The Contractor will then return to complete the remaining resurfacing repairs on River Walk next week. A further update will be posted early next week confirming the revised dates.

 

Playground Update

Washington Green

Play equipment has been installed, with the remaining footpath repairs scheduled for completion by close of business on Friday, 4th September.

 

A RoSPA safety inspection is scheduled to take place during the week commencing 7th September. Subject to a satisfactory inspection, the site fencing will then be removed and the playground opened.

 

College Avenue

Play equipment has been installed. Completion of the rubber safety surfacing is due to commence during the week commencing 7th September, followed by the installation of safety railings and completion of landscaping works.

 

The remaining works are expected to be completed within approximately 3 to 4 weeks.

 

Washington Drive

Civil works are currently underway, with installation of the play equipment scheduled to commence on 14th September.

The works are expected to be completed within approximately 4 weeks.

For any enquiries about our new community in Belcamp, please email community@glenveagh.ie

Site Updates September 2026